5/20/2020 - Greensburg Water Board meeting Tuesday night - Click here to print this information

Darren Burkhart from HNTB had an update on the water treatment plant. There are 619 days remaining on the project. New clarifiers and both foundations have been poured. The brick work has begun on the main water treatment plant building and the pump and electrical building. The roof was beginning to be installed but due to the weather has been stalled and cant start again until better weather. Next month they plan to focus on clarifiers and the treatment plant building. Burkhart also requested approval on the first change order of the project, a negative change order of $59,838. Motion to approve the change order was approved. There were 3 claims approved by the board.