The Greensburg Water Board met Tuesday evening. Darren Burkhart from HNTB provided an update on the new surface water treatment plant. He noted that 69 of the 824 shop drawings have been approved. They are responding to 31 requests for information with the possibility of some cost deductions. The second construction meeting took place on September 5th and call-ins every 2 weeks when there isn't a meeting have been scheduled. He covered several projects that are taking place, primarily related to the pump station, wet wells, and the clear well. Some of the work includes:

-Completion of excavation of the clear well

-Drilling steel piles for earth retention

-Excavating around piles

-Installing lagging between piles

-Drilling micro-piles

-Excavation for the pump station and wet well

-Preparation of concrete pour for the pump station slab

The board will hold its next meeting on October 15th at 6:00 pm at Greensburg City Hall.