8/21/2019 - Greensburg Water Board Meeting - Click here to print this information

The Greensburg Water Board met Tuesday evening. Darren Burkhart from HNTB provided an update on the new water treatment plant project. He noted that the groundbreaking took place on July 30th and was very successful. He stated that the contractors are on site full-time and trailers are in place with power. Currently, excavating is taking place for the wet well which will ultimately be about 25 feet deep. They will also put in earth retention facilities to hold back the earth along the southeast corner where the clear well will be constructed.

The contractors have started to put in the stone base for the clear well. The first concrete pour is expected to take place on August 28th. Rebar will be put in place with the forms set and stone pads in place. They will start on the clear well, wet well, and pump building with Plant 4 next. The clarifiers will start later and initially used for staging.

The first construction meeting took place on August 8th and monthly meetings will take place on the first Thursday of each month. During the meetings, they will approve pay requests to present to the board during their regular meeting.

The water board will hold its next meeting on September 17th at 6:00 pm at Greensburg City Hall.

Tom Flemming-WTRE News