4/10/2019 - Greensburg Water Board holds Special Session - Click here to print this information

The Greensburg Water Board met in Special Session Tuesday evening to open bids for the new water treatment plant project. Each company submitted a base bid along with an additional lump sum price if the clarifiers were post tensioning instead of cast in place. The companies/locations/and total base bid prices are:

-F.A. Wilhelm Construction/Indianapolis/$19,987,000

-Williams Brothers Construction/Peoria Heights, IL/$20,560,000

-Bowen Engineering Corporation/Indianapolis/$20,708,000

-Thieneman Construction, Inc/Westfield, IN/$20,719,000

-Reynolds Construction, LLC/Orleans, IN/$20,878,000

-Judy Construction Company/Cynthiana, KY/$21,811,000

-Adams Robinson Construction/Dayton, OH/$24,147,000

The board voted to take the bids under advisement to allow for a complete review of each bid. The board will make its decision during the regularly scheduled meeting that will take place on April 16th at 6:00 pm at Greensburg City Hall.

Tom Flemming-WTRE News