6/29/2018 - SR 9 Traffic Pattern Changes for Pavement Project - Click here to print this information

SHELBY CO., Ind. - The Indiana Department of Transportation (INDOT) is announcing traffic pattern changes on SR 9 between Broadway Street and the Shelby/Bartholomew county line for continued pavement work.

Traffic Shift between Broadway and Colescott streets

Beginning Friday, June 29 at 7 p.m., traffic will switch from two-way traffic (northbound and southbound) to only southbound traffic for 15 days. Traffic is anticipated to resume two-way traffic flow on July 14. Local access will be maintained during this traffic shift.

Traffic Shift between Hasecuster Lane and Shelby/Bartholomew county line

Beginning Friday, June 29 at noon, traffic will switch from only southbound traffic to two-way traffic (northbound and southbound) for 25 days. Traffic is expected to resume only southbound traffic on July 23 between County Road 750 S and the Shelby/Bartholomew county line. Local access will be maintained during this traffic shift.

About the SR 9 Pavement Project

The Indiana Department of Transportation (INDOT) awarded Milestone Contractors a $10.3 million contract to replace or resurface pavement on more than 12 miles of State Road 9 (Harrison Street in Shelbyville).

The road construction project will include:
Full-depth pavement repairs from Broadway Street (State Road 44) in Shelbyville to the Bartholomew County line
Resurfacing asphalt pavement from Broadway Street to McKinley Street in Shelbyville
Applying a thin concrete overlay from McKinley Street to the Bartholomew County line
Replacing storm sewer, concrete curb and gutter, and sidewalk